Speeders, utilities among challenges during Pat Bay overpass construction

Crosswalk, signage added to combat traffic woes during flyover build
web1_231206-pnr-hwy17update-cvr_1
The project to add a flyover at Keating Cross Road and the Pat Bay Highway in Central Saanich is on time and budget according to the Ministry of Transportation. (Christine van Reeuwyk/B次元官网网址 Staff)

The new overpass project at Keating Cross Road and Highway 17 is on time and budget, but not without its challenges, according to the Ministry of Transportation.

The $54.5-million contract was awarded to FlatIron Constructors Canada Ltd. this spring followed promptly with the start of construction.

The project will see the northbound turn lane onto Keating Cross Road replaced with a flyover overpass from Highway 17. Other work will also include installing a new sidewalk on Keating Cross Road, widening Keating Cross Road and the highway, realigning the southbound on-ramp, and closing the Highway 17 access at East Saanich and Martindale roads.

The ministry said traffic management is functioning well, but concerns have included trucks and tour buses on non-truck routes, speeding, pedestrian and cyclist safety and increased traffic on detour routes, the ministry said in a written statement to the Peninsula B次元官网网址 Review.

RELATED:

The ministry, District of Central Saanich and the contractor are tackling those issues including enhanced enforcement with provincial Commercial Vehicle Safety and Enforcement, RCMP and local police; revised and added signage including B次元官网网址渟hare the roadB次元官网网址 signs on Central Saanich and Tanner roads; and increased communications with truck and tour companies.

TheyB次元官网网址檝e also implemented traffic changes including prohibiting parking on the west side of Central Saanich Road from near Adam Kerr to Tanner and a new temporary crosswalk on Tanner Road.

B次元官网网址淭he ministry undertakes rigorous reviews to mitigate challenges during construction, which can be expected in any infrastructure project of this nature. One aspect of the project that has added complications is the extensive utility relocations. The ministry, contractor and utility providers have undertaken this work while limiting impacts to traffic and disruptions to services like power, water, sewer and telecommunications,B次元官网网址 the ministry statement reads.

RELATED:

The overpass project aims to provide safety improvements for commuters on the south Island B次元官网网址 more than 52,000 people drive through the area daily B次元官网网址 allowing vehicles to travel more safely and efficiently, lowering commute times and promoting regional economic growth.

ICBC crash data shows the prior configuration of the intersection had 20 crashes resulting in injury or death between 2018 and 2022. Another 25 resulted in property damage only.

The entire project is budgeted to cost $76.8 million, with $57.6 million coming from the province, $16.7 million from the federal government and $2.5 million from the District of Central Saanich.

Construction is expected to finish in spring 2025.



About the Author: Christine van Reeuwyk

Longtime journalist with the Greater Victoria news team.
Read more



(or

B次元官网网址

) document.head.appendChild(flippScript); window.flippxp = window.flippxp || {run: []}; window.flippxp.run.push(function() { window.flippxp.registerSlot("#flipp-ux-slot-ssdaw212", "Black Press Media Standard", 1281409, [312035]); }); }