View Royal council has approved More than $180,000 in spending to advance a project which proposes to replace and expand the West Shore RCMPB次元官网网址檚 detachment building in Langford.
The building is co-owned by the municipalities of View Royal, Langford, and Colwood, and the $186,720 from the townB次元官网网址檚 Police Capitalization Reserve approved by View Royal on Jan. 17 represents the townB次元官网网址檚 share of the $1.2 million required to further refine the projectB次元官网网址檚 plans and move it into the validation stage.
View RoyalB次元官网网址檚 approval of the funds to move the project along comes after Colwood council voted Jan. 9 to delay their decision until after the RCMP and Colliers, which produced a feasibility study and preliminary plan for the project, could meet with council and provide more information.
READ MORE: Colwood council delays vote to move forward on RCMP building expansion
View Royal Mayor Sid Tobias said council ultimately agreed with the reportB次元官网网址檚 finding that the existing building B次元官网网址 actually two buildings connected together, with one having been built in the 1960s and the other in the 1990s as an addition B次元官网网址 was no longer adequate to support the needs of the West Shore RCMP moving forward.
As the West ShoreB次元官网网址檚 population is projected to increase in the coming years, so too will the number of officers assigned to the detachment.
B次元官网网址漈he West Shore is growing at significant speed,B次元官网网址 said Tobias. B次元官网网址淚t is a huge expense for us, but if we had a joint municipal police force, we would have the same issue B次元官网网址 growth has a cost.B次元官网网址
Tobias said his concern with the project is the degree in which the public will be involved. He said he feels the public must be able to have their say in the new building. He plans on working with the soon-to-be-formed Joint Police Facilities Steering Committee B次元官网网址 which will include the mayors and CAOs of the three municipalities and oversee the project B次元官网网址 to determine how exactly that will happen.
Should it be approved, the project would be expected to total $82.4 million, plus or minus 25 per cent. A building size of 92,417 square feet together with 2.5 acres of parking would be needed in order to accommodate the next 20 years of growth, with opportunities for extra space to be leased out until needed in order to help recover some of the costs.
The project would see the older section of the building demolished and replaced, and the newer section of the building renovated, with neighbouring properties purchased to accommodate the expansion.
Should all three municipalities approve their budget contributions, the projectB次元官网网址檚 validation stage would run until mid-2023, with project approval and complete funding tentatively scheduled for the fall. Construction would occur in 2024 and 2025.