Getting operating rooms at Victoria General Hospital functional ahead of schedule took extra effort by a Greater Victoria construction company.
A broken water valve flooded the View Royal hospital in the early morning hours of July 10, closing four delivery and four operating rooms. All pediatric and C-section surgeries were completed as planned, but 12 adult surgeries were diverted to Royal Jubilee Hospital.
Brendan Grant, project manager at Downs Construction, an Esquimalt-based restoration and renovation company, said it wasnB次元官网网址檛 his week to be on call, but couldnB次元官网网址檛 defer when the hospital called him directly to help with the renovations.
Grant has a soft spot for the maternity ward. His first child spent 115 days in the neonatal intensive care unit and his second child was born with a hole in her heart and was cared for there as well. His wife also lived at the hospital for four months after their babies were born.
B次元官网网址淵ouB次元官网网址檇 be hard pressed to find me there [on his off-week] if the circumstances werenB次元官网网址檛 the same,B次元官网网址 he said.
Grant noted there was no time to waste, as there is a 72-hour window after a structure gets wet before mould starts to set in.
Grant and his crew pulled 22-hour days for nine days in a row to get the maternity ward back to normal as quickly as possible.
It took crews two days to set up the proper containment with negative air pressure to ensure no dust particles would get to other parts of the hospital.
The team cut out wet drywall, cleaned any dust behind it, put drywall back up, took the floor out, cleaned, put the floor back in, cleaned, and cleaned everything again once the containment was taken down.
He said if they stuck to regular 8 a.m. to 5 p.m. shifts it would have taken six weeks to complete the same amount of work. Grant said other project managers at Downs gave him their workers, rotating 12 workers through three shifts per day. His manager also gave him backup so they could continue working around the clock.
The team finished nearly all of the repairs by July 31, with the exception of the surgical daycare room as it is closed for the summer.
B次元官网网址淚 was glad we got it done and we kept it up and running,B次元官网网址 Grant said.
The team worked with nurses and hospital staff to try to eliminate the chance of a mother giving birth to the sound of drilling across the hall.
B次元官网网址淲e tried to minimize it as much as we could and just tried to co-ordinate with the nurses to let them know what times things were going to be loud,B次元官网网址 Grant said.
Like us on and follow us on